South EndZone

USC/ISU
First on the USC thing. I don't think there was any effort to copy USC's uniforms, however anyone who says they are not at all alike is delusional I believe our administrators probably were looking for a updated design using the Iowa game throwbacks as a base design and being that ISU and USC basically have the same color...guess what.

I think administrators have tried to get away from this problem to some extent. The use of the white road uniforms. They even tried a gold jersey a few years ago but few people liked it. I would be surprised if we didn't change our home uniform just enough over the next few years to get away from the USC comparison.

SEZ
As for the stadium. Facilities is my bread and butter. I worked for the university in a capacity that allowed for me to become intimate with our facilities and opened up opportunities to see and hear plans and ideas that were on the table. I've been away from the university for a while but I think I have a pretty good feel for what is going on.

The SEZ is going to happen, and the students will be moved to the endzone. The band will most likely be moved with the students. The space in the endzone will remain cheep seats so why not put the students there when we can get more out of the seats on the east side. A portion of the current student section will be visitors section to separate the two factions. Majority of people who pay big money for tickets don't want to be near the students (see below about press box).

​Press box
The press box has been mentioned by some "insiders" on this board as one of the priorities along with the SEZ. Of course after the SEZ what is left? I could list off dozens of projects that could be done and are in the works, but at this point it is more like coming up with a wish list instead of a must do list.

I do know that as of 2010 we were near equilibrium for suites with supply being just behind demand. It just isn't a wise move to spend millions to add a bunch of suites that may or may not sell. The press area is cramped in our press box as well as the administration space, but is it worth the cost? Actually the two areas in our press box that probably need the most attention are the TV broadcast area and technical and administrative areas. Now only the first floor is suites, second floor is open press area and the top floor is TV/Radio broadcast and coaches suites.

Originally there were plans to add suites to the East side just like the west side. There were a number of reasons why this didn't happen including cost and student section. However, after the SEZ is built I would be looking for new suites on the east side along with a remolded press box that will expand 3rd floor operations onto the 1st floor.

I just don't see us making any big changes to the press box for some time. The athletic department will have to pay down some bills and ISU football will have to become more than a 6 win team. Several projects get paid off in 2016, maybe sometime after then...maybe.

So when you say SEZ will happen... will it be the first thing and if so will it happen prior to the 2016 debt freedom?
 
So when you say SEZ will happen... will it be the first thing and if so will it happen prior to the 2016 debt freedom?

Don't know and don't know. Given what I knew before all the conference reallingment, TV deals, etc., I would say that the SEZ will happen before the press box. I will say that most likely we won't see anything done until 2014 and it will take two years to complete making 2016 the first season.

Now there are so many things that can change on a daily basis. Donations my move things up. Coaches salaries could delay things.

Bring people back down to earth a little.

JP will have to get permission from the BOR before anything could be started. JP has permission to plan it and that is all. He will have to get permission to go beyond planning. At this point that has not happened and JP will not make an announcement about the endzone without prior approval. The next BOR meeting is in February so there will not be an announcement after the bowl game.

I personally don't think they will begin construction this year. February is getting a little late to be making the big changes that will be required, from a ticket standpoint.
 
Are there any estimations as to what a two level bowles in SEZ would bring capacity up to or how long it would take to build?
 
Are there any estimations as to what a two level bowles in SEZ would bring capacity up to or how long it would take to build?

I'll post these here. There have been some changes made, but these are the original plans that came out back in 08 I think.

Lower Deck

Upper Deck

Also I've been doing some digging and this might be happening sooner than I said. Sounds like the athletic department has been getting things ready for this over the past year.
 
  • Like
Reactions: Cincyclone
:wideeyed:

muppetskermitfreakout.gif
 
I'll post these here. There have been some changes made, but these are the original plans that came out back in 08 I think.

Lower Deck

Upper Deck

Also I've been doing some digging and this might be happening sooner than I said. Sounds like the athletic department has been getting things ready for this over the past year.


Thanks for all the info. Do you think its possible an announcement could come this offseason for a fundraising effort and then they start building following next season? Or is that too optimistic?
 
From the looks of it, we were able to do a early repayment of several projects. The renovations to Hilton and JT were paid off this past year and some of other projects were paid off using a portion of the bond for the training facility. These were several of the items that were going to get paid off in 2016.

A couple of other interesting notes. The Athletic department is expecting a decrease in ticket sales next year. Not sure why, but they are allowing themselves nearly a $1.5 million cushion over this year and half million under previous budget. Also $4 million is planned of capital improvements over last year (I'm guessing part of that is Jacobson renovations, but 4 million is a lot to renovate a building of that size. That is almost the cost of the scoreboard.
 
Last edited:
From the looks of it, we were able to do a early repayment of several projects. The renovations to Hilton and JT were paid off this past year and some of other projects were paid off using a portion of the bond for the training facility. These were several of the items that were going to get paid off in 2016.

A couple of other interesting notes. The Athletic department is expecting a decrease in ticket sales next year. Not sure why, but they are allowing themselves nearly a $1.5 million cushion over this year. Also $4 million is planned of capital improvements over last year (I'm guessing part of that is Jacobson renovations, but 4 million is a lot to renovate a building of that size. That is almost the cost of the scoreboard.
That's odd.
Considering we have a favorable home schedule, with UNI, Iowa, and Texas.
And if Sam plays out of his mind for the bowl game, there will be some nice excitement for next season.
 
Listen to this. 70 mil for a SEZ and a press box. We just spent close to 20 mil in concourses and video board. That's 90 mil for renos. Couldn't we have built a brand new kick *** stadium for that???

Thing also is if they built new we would need somewhere else to play assuming the new stadium stays in the same location. No location in Ames is good enough unless they build it in the floodplain across the street. Gophers played in the dome, Baylor will be a new location, and the Vikings are using TCF stadium while their new one is built.
 
Thanks for all the info. Do you think its possible an announcement could come this offseason for a fundraising effort and then they start building following next season? Or is that too optimistic?

Meh...JP is going to have to have the money secured for the BOR to approve it and as I said before, it won't be "announced" until after it's approved, making fundraising (although helpful) unnecessary for the project itself to continue.

It seems like these usually go before the BOR about 6 months before JP wants to start the construction. It can be speed up, but when your talking a bigger project like this they probably want to have a nice cushion so that they can get everything prepared. I would be looking for announcement this spring for construction to start during or after the season if one is going to be made.

It is possible they will start taking out the scoreboard and endzone bleachers toward the end of the season so the earth moving equipment can start late November. That might explain the small drop they are expecting in ticket sales for next year.
 
That's odd.
Considering we have a favorable home schedule, with UNI, Iowa, and Texas.
And if Sam plays out of his mind for the bowl game, there will be some nice excitement for next season.


Well...one explanation for a decrease in ticket sales would be if the South bleachers have been taken out...for some reason....and not able to be sold all season.....

:yes::yes:
 

Help Support Us

Become a patron