Oh yeah, paint and light bulbs. Woohoo.
Okay, I'm not sure why your so disappointed in what JP has done with facilities, I can understand being disappointed in the wins/loss record, but facilities?
Let's give you a reality check, Original Facility Master Plan compared to what has happened:
Football Stadium Suites/Club/Gates
- Originally planned for Fall 2008, $10 million
- Completed Fall 2008, $19 million
=Completed on time, $9 million over original plan
Basketball Practice Facility
- Originally planned for Fall 2009, $25 million
- Completed Fall 2009, 8 million
=Completed on time, $17 million less than originally planned
Hilton Renovations
- Originally planned for Fall 2010, $35 million
- Not completed
=Not originally planned to be completed for another year
Jack Trice South End Zone project
- Originally panned for Fall 2010 to include east side concessions, $25 million
- East side concession completed Fall 2009, $11 million
- No known timeline for South End Zone, $55 million
=Partially completed a year ahead of schedule, no timeline for finishing, total project cost is $41 million over original plan
Student Recreation Center
- Originally no timeline, unknown cost
- Project will be completed Fall 2011, $52.8 million
=Completed way ahead of what was originally thought
Hilton Atrium/Office/Gateway Complex
- Originally no timeline, unknown cost
- No known timeline, unknown cost
=No timeline, no known cost
All project have been completed on or ahead of schedule so far.
Original plans cost to date: $35 million
Current cost to date: $38 million
Recreation Center
Master Plan
Now, come next fall, you may have more of an argument. JP originally planned for $60 million in improvements for 2010, which to do those same improvements will now cost $90 million. Until then, you can't criticize him for not completing facilities that wasn't planned to be completed yet. He has done everything, to date, that he promised. Remember, we didn't hear the announcement for the current projects until late last year.